The Venice extension was designed to supply gas to Venture Global LNG’s Plaquemines liquefied natural gas (LNG) export plant in Louisiana, which is under construction and expected to enter service between 2024 and 2026.
The U.S. Federal Energy Regulatory Commission (FERC) said it granted Texas Eastern’s March 26 request to commence service of the 3-mile (4.8-kilometer), 36-inch (91.4-centimer) Venice extension pipeline.
The U.S. Energy Information Administration (EIA) has said the Venice extension would have a capacity of around 1.3 billion cubic feet per day (bcfd) and cost about $500 million.
Plaquemines is designed to turn about 2.6 bcfd of gas into LNG.
Other pipes under construction that will also provide gas to Plaquemines include Texas Eastern’s Gator Express and U.S. energy company Kinder Morgan’s Tennessee Gas Evangeline projects.
One billion cubic feet of gas is enough to supply about 5 million U.S. homes for a day.
(Reporting by Scott DiSavino in New York Editing by Matthew Lewis)